Central Coast Quarter - HDA Scheme
Two towers with 394 apartments and a hotel, Mann Street, Gosford
Where it is in the process
At assessment
What it proposes
AI summary. Written from this project's page and its Environmental Impact and Rezoning Statement on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Two towers with 394 apartments and a hotel, Mann Street, Gosford
The proponent proposes two towers of 36 and 42 storeys above a retail podium at 26-30 Mann Street, Gosford, in the Central Coast Council area. The environmental impact and rezoning statement (EIRS) describes 394 apartments, of which 98 are affordable, a 152 key hotel and 2,153 m² of retail floor area. It also seeks a concurrent change to the State planning policy for the Central Coast, raising the floor space ratio from 3.5:1 to 9.5:1. The site is 5,788 m². No capital investment is stated.
The Secretary's environmental assessment requirements were issued on 20 Aug 2025, and the EIRS is dated 20 Feb 2026. The proposal was exhibited and drew 17 submissions: 14 objecting and 3 supporting. The proponent has responded to submissions, and the department is now assessing the case. Next come the department's assessment report and a decision.
- Apartments
- 394 apartmentsEnvironmental Impact and Rezoning Statement
- Affordable apartments
- 98 apartmentsEnvironmental Impact and Rezoning Statement
- Hotel rooms
- 152 keysEnvironmental Impact and Rezoning Statement
- Retail floor area
- 2,153 m²Environmental Impact and Rezoning Statement
- Site area
- 5,788 m²Environmental Impact and Rezoning Statement
- Taller tower
- 42 storeysEnvironmental Impact and Rezoning Statement
- Shorter tower
- 36 storeysEnvironmental Impact and Rezoning Statement
- Submissions objecting
- 14 submissionsPortal page
The department's description
Additional 273 apartments (a total of 505 apartments) across two 39 storey towers, including 20% GFA for affordable housing. Concurrent Planning Proposal.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
17 submissions: 15 from the public, 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
78 documents in 8 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
SEARs3
EIS45
- Appendix A SEARs Requirements Table
- Appendix AA Acid Sulfate Soils Management Plan
- Appendix B Mitigation Measures
- Appendix BB Water Management Plan
- Appendix C Statutory Compliance Table
- Appendix CC Civil Engineering Plans
- Appendix D Alternative Design Excellence Strategy
- Appendix DD Waste Management Plan (C&O)
- Appendix E DRP Minutes
- Appendix EE Statement of Heritage Impact
- Appendix F Architectural Drawings
- Appendix FF Social Impact Assessment
- Appendix G Design Report
- Appendix GG Infrastructure Delivery, Management and Staging
- Appendix H Survey Plan
- Appendix HH Aviation Impact Assessment
- Appendix I BCA Compliance Report
- Appendix II Engagement Report
- Appendix J Accessibility Report
- Appendix JJ Public Art Strategy
- Appendix K Wind Report
- Appendix KK Structural Report
- Appendix L Visual Impact and View Sharing Assessment
- Appendix LL Preliminary Construction Management Plan
- Appendix M CPTED Report
- Appendix MM CHP Letter
- Appendix N Arboricultural Impact Assessment
- Appendix O Landscape Report and Plans
- Appendix OO Groundwater Modelling Report
- Appendix P ESD Report & Net Zero Statement
- Appendix PP Fire Engineering Letter
- Appendix Q BASIX Certificate
- Appendix QQ Aboriginal Cultural Heritage MP
- Appendix R NABERS Embodied Emissions Materials Form
- Appendix RR Detailed Site Investigation 2021
- Appendix S Section J Assessment
- Appendix T NABERS Statement
- Appendix U Transport and Accessibility Impact Assessment
- Appendix V Connecting with Country
- Appendix W Reflectivity Report
- Appendix X BDAR Waiver
- Appendix Y Noise and Vibration Impact Assessment
- Appendix Z Geotechnical Assessment
- Application Form
- Environmental Impact and Rezoning Statement
Response to Submissions20
- Appendix A - Architects Response to Key Issues Report
- Appendix B - Landscape Plans & Plant Schedule
- Appendix C - Architectural Plans & Schedule of Changes
- Appendix D - Section 5.44 Building Height Mapping Changes
- Appendix E - Pedestrian Wind Study
- Appendix F - Visual Impact Assessment
- Appendix G - Noise Impact Assessment
- Appendix H - Updated Civil Engineering Plans
- Appendix I - Infrastructure DD Report
- Appendix J - JHA Response
- Appendix K - CHP Letter
- Appendix L - Arboricultural Impact Assessment
- Appendix M - Loading Dock Management Plan
- Appendix N - Swept Path Analysis
- Appendix O - Lift Analysis
- Appendix P - Hotel Operator Letter
- Cover Letter - Response to DPHI RFI on RTS
- Key Issues Letter
- Request RTS Letter
- Revised Response to Submissions Report
Agency Advice5
Additional Information1
What's near it
Where it is
- Suburb
- Gosford
- Council area
- Central Coast
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.