Part 4 development

Camden Gas Stage 2D - Sugarloaf

Decided: approved on 7 Oct 2005Energy: other

Where it is in the process

Approved on 7 Oct 2005

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination7 Oct 2005 (done)
  10. Approved7 Oct 2005

What it proposes

The portal gives no description.

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Administrative ChangeDA75-4-2005-Mod-1

Decided: approved by the Minister

Its page on the Planning Portal

Mod 3 - Administrative ChangeDA75-4-2005-Mod-3

Decided: approved on 20 Apr 2011 by the department (deputy director-general)

Its 8 documents

Its page on the Planning Portal

Mod 2 - Administrative ChangeDA75-4-2005-Mod-2

Decided: approved on 10 Jan 2010 by the department (executive director)

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Recommendation1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

5 documents in 2 folders, each on the NSW Planning Portal

Determination3

See the 3 documents on the Planning Portal

Management Plans and Strategies2

See the 2 documents on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.