Cadia East Gold/Copper Project

Decided: approved on 6 Jan 2010Mining

Where it is in the process

Approved on 6 Jan 2010

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination6 Jan 2010 (done)
  8. Approved6 Jan 2010

What it proposes

The department's description

To develop an open cut mine and associated infrastructure to extract approximately 562 million tonnes of gold and copper ore until 2031.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

21 submissions: 21 from the public

Object8
Support10
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

17 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 16 – NTSF recovered sand buttressingMP06_0295-Mod-16

Decided: approved on 16 Oct 2026 by the department (executive director) · 27 submissions

Use recovered sand tailings for NTSF buttressing and deposit the excess material into the STSF.

Its 46 documents

46 documents in 8 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application12

See the 12 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice12

See the 12 documents on the Planning Portal

Additional Information14

See the 14 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 17 - Confirmation of Approved Disturbance FootprintMP06_0295-Mod-17

Decided: approved on 6 Feb 2026 by the department (director)

Confirmation of approved disturbance footprint.

Its 9 documents

9 documents in 5 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 15 - Various including tailings dam embankment upgradeMP06_0295-Mod-15

Decided: approved on 31 Jan 2025 by the department (executive director) · 29 submissions

Includes changes to tailings dam embankment footprint, infrastructure areas, development of the Ridgeway Mine, realignment of Panuara Road, new site access roads, tailings pilot plant, ventilation shafts and more (refer to scoping letter)

Its 88 documents

Its page on the Planning Portal

MOD 14 - Increased Processing RateMP06_0295-Mod-14

Decided: approved on 13 Dec 2021 by the department (executive director) · 43 submissions

Includes increasing ore processing rate from 32 Mtpa to 35 Mtpa, upgrading ore processing infrastructure & Southern Tailings Storage Facility (TSF), repairing/using the Northern TSF, constructing/using a Sodium Hydrosulphide Production Plant on-site.

Its 43 documents

Its page on the Planning Portal

MOD 13 - Cadia Hill Tailings CompletionMP06_0295-Mod-13

Decided: approved on 20 Dec 2019 by the department (director) · 11 submissions

Increase tailings level of Cadia Hill open pit to full capacity (approx. 177Mt over 7 yrs), decommission vent adit VR101 & install new vent adit and construct additional buttressing for the STSF embankment.

Its 14 documents

14 documents in 4 folders, each on the NSW Planning Portal

Modification Application8

See the 8 documents on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Cadia Mine MOD 12 - Tailings IncreaseMP06_0295-Mod-12

Decided: approved on 24 Sep 2018 by the department (director)

/

Its 6 documents

Its page on the Planning Portal

Cadia Mine MOD 11 - Hill TailingsMP06_0295-Mod-11

Decided: approved on 20 Apr 2018 by the department (executive director)

/

Its 12 documents

Its page on the Planning Portal

Cadia Mine MOD 10 - Molydbenum Plant RelocationMP06_0295-Mod-10

Decided: approved on 12 Apr 2018 by the department (director)

/

Its 16 documents

Its page on the Planning Portal

Cadia Mine MOD 9 - Cadia East GoldMP06_0295-Mod-9

Decided: approved on 21 Apr 2017 by the department (director)

/

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Cadia Mine MOD 8 - Cadia East GoldMP06_0295-Mod-8

Decided: approved on 28 Apr 2016 by the department (director)

/

Its 6 documents

6 documents in 2 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Cadia Mine MOD 6 - Cadia East GoldMP06_0295-Mod-6

Decided: approved on 31 Aug 2015 by the department (executive director) · 18 submissions

Cadia East Gold (Mod 6)

Its 42 documents

Its page on the Planning Portal

Cadia Mine MOD 7 - Cadia East GoldMP06_0295-Mod-7

Decided: approved on 4 Aug 2015 by the department (director)

/

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EIS1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Cadia Mine MOD 5 - Surface Preconditioning (blasting)MP06_0295-Mod-5

Decided: approved on 14 Aug 2014 by the department (executive director) · 2 submissions

/

Its 7 documents

Its page on the Planning Portal

Mod 4 - Surface Preconditioning (hydraulic)MP06_0295-Mod-4

Decided: approved with conditions on 5 May 2014 by Dir(MDA)

Its 8 documents

Its page on the Planning Portal

MOD 3 - Cadia Road PipelineMP06_0295-Mod-3

Decided: approved on 9 Aug 2011 by Dir(MDA)

-

Its 2 documents

2 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EA1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 2 - Blayney Dewatering FacilityMP06_0295-Mod-2

Decided: approved on 25 Oct 2010 by Dir(MDA)

-

Its 6 documents

Its page on the Planning Portal

MOD 1 - Cadia Hill DeclineMP06_0295-Mod-1

Decided: approved on 25 Oct 2010 by Dir(MDA)

Cadia East Gold (Mod 1)

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.