Cabbage Tree Road Sand Quarry
Where it is in the process
Approved on 9 May 2018
What it proposes
The department's description
The project would involve clearing 42.25 hectares (ha) of land in order to establish an extraction area, site facilities, processing and stockpile areas and a quarry entry and deceleration and acceleration lanes on Cabbage Tree Road.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
114 submissions: 109 from the public and 5 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
4 changes to the project after its decision, each assessed as a case of its own, newest first.
Mod 3 Extension and AmendmentsSSD-6125-Mod-3
The modification would involve increasing disturbance by 6.6%, increasing production to 580,000t, amending the Biodiversity Offset Strategy, clarifying extraction method, improving timber management, updating the Statement of Commitments
Its 20 documents
20 documents in 6 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application3
Response to Submissions4
Agency Advice9
Additional Information2
Modification 4 Western ExtensionSSD-6125-Mod-4
The modification seeks to extend quarrying west into Lot 9 DP 239608, and make minor amendments to the existing approved sand quarry.
Its 36 documents
36 documents in 7 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application9
Response to Submissions8
Agency Advice10
Additional Information4
Determination3
Consolidated Consent1
Cabbage Tree Road Sand Quarry MOD 2 - Sand WashSSD-6125-Mod-2
Application to install a sand wash plant and ancillary infrastructure on the site
Its 11 documents
11 documents in 5 folders, each on the NSW Planning Portal
Modification Application2
Agency Advice4
Additional Information2
Determination2
Consolidated Consent1
Cabbage Tree Road Sand Quarry MOD 1 - Sand TrialSSD-6125-Mod-1
A proposal to allow 5,000 tonnes of sand to be sent to Sibelco's Salt Ash Plant, prior to the completion of the site entry and weighbridge. Processed sand would be transported to a Sydney factory to test suitability for glass manufacture.
Its 9 documents
9 documents in 4 folders, each on the NSW Planning Portal
Modification Application3
Agency Advice3
Determination2
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
203 documents in 14 folders, each on the NSW Planning Portal
Request for DGRS3
Application2
Submissions64
Response to Submissions36
Recommendation3
Determination4
Management Plans and Strategies20
Agreements5
Independent Reviews and Audits3
Notifications1
Other Documents3
What's near it
Where it is
- Suburb
- Williamtown
- Council area
- Port Stephens
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.