Brookhollow Avenue Data Centre Expansion, Norwest
Data centre expansion at 3 Brookhollow Avenue, Norwest
Where it is in the process
At assessment
What it proposes
AI summary. Written from this project's page and its EIS - 3 Brookhollow Avenue, Norwest on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Data centre expansion at 3 Brookhollow Avenue, Norwest
The proponent proposes to build and operate an expansion of an existing data centre at 3 Brookhollow Avenue, Norwest, in The Hills Shire. The environmental impact statement (EIS), dated May 2026, describes new buildings, back-up power systems, cooling, parking and landscaping, and some tree removal. No capital investment, floor area, building height or job numbers are stated in the text available.
The EIS was lodged on 27 May 2026 and exhibited. The case drew 59 submissions: 48 objecting, 3 supporting and 8 commenting. The proponent has since responded to the submissions with updated studies. The department is now assessing the project with advice from other agencies. Next, it prepares an assessment report and recommendation, and the project is then decided.
- Public submissions
- 59 submissionsPortal page
- Submissions objecting
- 48 submissionsPortal page
The department's description
Construction and operation of an expansion to an existing data centre.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
59 submissions: 54 from the public, 4 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
96 documents in 7 folders, each on the NSW Planning Portal
Early Consultation1
Notice of Exhibition1
Request for SEARs1
EIS45
- A1 - SEARs Table
- A10 - Visual Impact Assessment
- A11 - Landscape Masterplan Report
- A12 - Landscape Plans
- A13 - Arboriculture Impact Assessment
- A14 - Traffic Report
- A15 - Preliminary CTMP
- A16 - Green Travel Plan
- A17 - ESD Assessment
- A18 - Embodied Emissions Form
- A19 - BDAR
- A2 - Statutory Compliance Table
- A20 - Back-Up Power
- A21 - AQIA
- A22 - Noise and Vibration Assessment
- A23 - GIA
- A24 - Water Management Report
- A25 - Civil Plans
- A26 - Flood Assessment Report
- A27 - Geotechnical Report
- A28 - Preliminary Hazards and Risks Assessment
- A29 - Infrastructure Requirements and Utilities
- A3 - Mitigation Measures
- A30 - Detailed Site Investigation
- A31 - LTEMP
- A32 - Waste Management Plan
- A33 - ACHAR - Redacted
- A34 - SOHI
- A35 - CWC Report
- A36 - Engagement Report
- A37 - SIA
- A38 - Construction Phasing Plan
- A39 - BCA Assessment
- A4 - Clause 4.6 Variation
- A40 - Fire Engineering Assessment
- A41 - Access Report
- A42 - ASS Report
- A43 - Archaeological Technical Report
- A5 - THDCP 2012 Assessment
- A6a - Site Survey
- A6b - Site Survey - Utility
- A7 - EDC Report - 3 Brookhollow Avenue, Norwest
- A8 - Architectural Plans
- A9 - Architectural Design Report
- EIS - 3 Brookhollow Avenue, Norwest
Response to Submissions38
- A1 - Consolidated Submissions Register
- A10 - Updated ESD Report
- A11 - Updated Hazards and Risks Assessment
- A12 - Peer Review
- A13 - Updated Architectural Plans
- A14 - Updated Architectural Design Report
- A15 - Updated Visual Impact Assessment
- A16 - Updated Landscape Design Report
- A17 - Updated Landscape Plans
- A18 - Greenhouse Gas Emissions
- A19 - Updated IWMP
- A2 - Updated Mitigation Measures
- A2 - Updated Mitigation Measures
- A20 - Updated Civil Plans
- A21 - RtS Traffic Response
- A22 - Updated PCTMP
- A23 - Addendum Waste Management Report
- A24 - Addendum BCA Report
- A25 - Updated ASSA
- A26 - Updated Geotechincal Investigation Report
- A27 - Updated Groundwater Impact Assessment
- A28 - Updated Social Impact Assessment
- A29 - Updated BDAR
- A3 - Response to Agency Submissions
- A4 - Response to Public Submissions
- A5 - Clause 4.6 Variation
- A6 - Updated NVIA
- A7 - Updated AQIA
- A8 - Updated Back-Up Power Report
- A9 - Updated Infrastructure Report
- NAL consent - SYD1 Stage 2
- Request RTS Letter
- Response to Submissions Report
- Stamped NAL Architectural Plans - Part 1
- Stamped NAL Architectural Plans - Part 2
- Stamped NAL Landscape Masterplan Report
- Stamped NAL Landscape Plans
- Stamped NAL Traffic Report
What's near it
Where it is
- Suburb
- Bilpin
- Council area
- The Hills Shire
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.