A 186 MW battery on Brandy Hill Drive, Brandy Hill

Under way: at prepare eisEnergy: batteriesDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 186 MW battery on Brandy Hill Drive, Brandy Hill

The proponent proposes a battery energy storage system with a capacity of 186 MW and 620 MWh at 86 Brandy Hill Drive, Brandy Hill, in the Port Stephens council area. It would have 100 battery containers and 25 inverter containers, and connect to two existing 132kV transmission lines near the Brandy Hill Substation. The development site is about 106.04 ha. The estimated capital investment is $222M. The scoping report expects about 100 construction jobs and 2 to 4 full-time operational jobs.

The case is at the stage where the proponent prepares an environmental impact statement (EIS). The Secretary's environmental assessment requirements (SEARs) have been issued, and agencies have given advice on them; no dates are given. No public submissions have been made yet. Next, the EIS is to be exhibited for public comment. The proponent then responds to submissions and the department assesses the project. The scoping report says construction is to begin in 2027 and take 12 months.

Capital investment
$222MScoping Report
Battery power capacity
186 MWPortal page
Battery storage capacity
620 MWhPortal page
Construction jobs
100 jobsScoping Report
Operational jobs (upper estimate)
4 jobsScoping Report
Development site area
106.04 haScoping Report
Battery containers
100 containersScoping Report

The department's description

Construction, operation and decommissioning of a 186 MW / 620 MWh battery energy storage system (BESS) and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.