On the map
State significant development

Blakebrook Quarry

Decided: approved on 24 Nov 2009Quarries

Where it is in the process

Approved on 24 Nov 2009

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination24 Nov 2009 (done)
  8. Approved24 Nov 2009

What it proposes

The portal gives no description.

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Blakebrook Quarry Mod 4 - Asphalt Plant Production IncreaseMP07_0020-Mod-4

Under way: at assessment · 22 submissions

Increase in asphalt production and transportation limits from 50,000 tonnes per annum (tpa) to 100,000 tpa. Change in asphalt plant operating hours to allow 24/7 operations.

Its 17 documents

17 documents in 5 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Early Consultation2

See the 2 documents on the Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice7

See the 7 documents on the Planning Portal

Its page on the Planning Portal

Mod 2MP07_0020-Mod-2

Withdrawn: withdrawn

Its 2 documents

2 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Withdrawal1

See the document on the Planning Portal

Its page on the Planning Portal

Blakebrook Quarry MOD 3 - Asphalt PlantMP07_0020-Mod-3

Decided: approved on 20 Jul 2021 by the department (director) · 5 submissions

Modification application to amalgamate the Asphalt Plant (ancillary activity) with the Blakebrook Quarry approval. The applications also proposes a number of changes to the project commitments and conditions of approval to reflect true operation

Its 16 documents

16 documents in 6 folders, each on the NSW Planning Portal

Response to Submissions5

See the 5 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Recommendation3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Blakebrook Quarry MOD 1 - Cap Rock MiningMP07_0020-Mod-1

Decided: approved on 18 Sep 2017 by the department (director)

/

Its 9 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.