Beech Road Multi-level Warehouse, Casula
A multi-level warehouse at 200 Beech Road, Casula
Where it is in the process
Approved on 23 Feb 2026
What it proposes
AI summary. Written from this project's page and its Assessment Report and Instrument of Determination on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A multi-level warehouse at 200 Beech Road, Casula
The project is a two-level warehouse and distribution centre at 200 Beech Road, Casula, in the Liverpool City Council area, on a site of about 3.85 ha that now holds a Bunnings store. It has eight tenancies and a total gross floor area of 28,015 m², with a main building up to 22.2 m high. The department gives an estimated development cost of $109,834,105 and 13 operational jobs. It would operate 24 hours a day, 7 days a week.
The environmental impact statement (EIS) was exhibited from 15 Nov 2024 to 12 Dec 2024 and drew 3 submissions: 1 objecting and 2 commenting. The proponent responded in May 2025 and gave more information in June and November 2025. The department recommended approval, and its Director approved the project on 23 Feb 2026, with conditions. Next, the proponent must meet those conditions before and during construction.
- Estimated development cost
- $109.8MAssessment Report
- Gross floor area
- 28,015 m²Assessment Report
- Maximum building height
- 22.2 mAssessment Report
- Site area
- 3.85 haAssessment Report
- Tenancies
- 8 tenanciesAssessment Report
- Operational jobs
- 13 jobsAssessment Report
The department's description
The proposal is for the construction and operation of a multi-level warehouse and distribution facility located at 200 Beech Road, Casula.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
3 submissions: 1 from the public and 2 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
83 documents in 7 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs3
EIS42
- 20240619 ASIC Extract - Perpetual Corporate Trust Limited
- Appendix 1 - SEARs
- Appendix 10 - Transport and Accessibility Impact Assessment
- Appendix 11 - Landscape Plans
- Appendix 12 - ESD Report
- Appendix 12 - Net Zero Statement
- Appendix 13 - NABERS Embodied Materials Form
- Appendix 14 - Biodiversity Development Assessment Report
- Appendix 15 - Air Quality Assessment
- Appendix 16 - Noise and Vibration Impact Assessment
- Appendix 17 - Geotechnical Assessment
- Appendix 18 - Civil Report
- Appendix 19 - Acid Sulfate Soil and SMP
- Appendix 2 - QS Letter
- Appendix 20 - Economic Impact Assessment
- Appendix 21 - Flood Risk Assessment
- Appendix 22 - Premilinary Risk Screening
- Appendix 23 - Preliminary Site Investigation
- Appendix 24 - Construction Waste Management Plan
- Appendix 24 - Operational Waste Management Plan
- Appendix 25 - Hazardous Materials Survey
- Appendix 26 - ACHAR - Public
- Appendix 27 - Statement of Heritage Impact
- Appendix 28 - Social Impact Assessment
- Appendix 29 - Service Infastructure Assessment
- Appendix 30 - Bushfire Confirmation
- Appendix 31 - Engagement Report
- Appendix 32 - Consent Reference 2973_00
- Appendix 33 - Pipeline Hazard Analysis
- Appendix 34 - Arborist Impact Assessment
- Appendix 35 - Clause 4.6 Variation to Development Standard
- Appendix 36 - NABERS Agreement to Rate
- Appendix 4 - Architectural Drawings
- Appendix 5 - Design Report
- Appendix 6 - Survey Plan
- Appendix 7 - BCA Regulatory Complaince Report
- Appendix 8 - Accessibility Report
- Appendix 9 - Visual Imapct Assessment and Analysis
- Application_20241028021453
- Environmental Impact Statement - Lot 100 Casula
- NSW POA certified 31072024
- Owners consent form
Response to Submissions5
Agency Advice27
- Appendix 1 - Revised Architectural Plans 23/06/25
- Appendix 2 -Amended Quantitive Risk Assessment
- Appendix D1 - Updated Architectural Drawings
- Appendix D12 - Contamination Investigation Process Letter
- Appendix D13 - Height Clearance Requirements
- Appendix D2 - Design Report
- Appendix D3 - Updated Clause 4.6 Variation Request
- Appendix D5 - Updated BDAR
- Appendix D6 - Operational Traffic Daily Profile
- Appendix D7 - Access and Circulation Diagrams
- Appendix D8 - Updated VIA
- Appendix D9 - Updated Landscape Plans
- BCS EIS response 18.12.2024
- CPHR RTS response 22.05.25
- Council EIS Response 11.12.2024
- Council RTS response 16.05.2025
- Council additional information response 7/07/2025
- HNSW EIS response 6.12.2024
- HNSW RtS response 13.05.25
- Heritage NSW EIS response 4.12.2024
- NSW F&R RtS response 12.05.25
- NSWF&R EIS response 25.11.24
- RFI Response Letter 23/06/25
- RTS Report - Beech Road Warehouse
- Sydney Water EIS response 5.12.2024
- Sydney Water EIS response info sheet 5.12.2024
- TfNSW EIS Response 26.11.2024
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.