Where it is in the process
Approved on 8 Apr 2026
What it proposes
AI summary. Written from this project's page and its Assessment Report and Conditions of Approval on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Concept plan for up to 12 towers at BaptistCare, Macquarie Park
The proposal is a concept plan for the BaptistCare site at 157 Balaclava Road, Macquarie Park, in the City of Ryde. It sets six building envelopes for 12 towers, from 48.8 m to 86.5 m high, with a maximum gross floor area of 198,427 m². Uses include market and affordable housing, seniors housing, co-living, health services, childcare, commercial space and public open space. An indicative scheme shows 922 apartments. The estimated development cost is $2,500,153,633. It is a concept only: no building work is approved.
The environmental impact statement was exhibited from 16 Dec 2022, and an amendment report from 3 Jun 2025 to 1 Jul 2025. The portal records 44 submissions: 37 objecting, 1 supporting and 6 commenting. The department recommended approval, and its Executive Director approved the concept for the Minister on 8 Apr 2026, with conditions. Each stage now needs its own development application.
- Estimated development cost
- $2.5bnAssessment Report
- Maximum site-wide gross floor area
- 198,427 m²Conditions of Approval
- Tallest building envelope
- 86.5 mConditions of Approval
- Shortest building envelope
- 48.8 mConditions of Approval
- Apartments in indicative scheme
- 922 dwellingsAssessment Report
- Minimum public open space
- 10,982 m²Conditions of Approval
- Construction jobs
- 2,600 jobsAssessment Report
- Ongoing jobs
- 460 jobsAssessment Report
The department's description
Concept proposal for the redevelopment of the BaptistCare site as a mixed-use development, including seniors housing, student accommodation, build to rent and build to sell residential flat buildings, a school, retail and community land uses.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
44 submissions: 40 from the public, 3 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
MOD 1 - BaptistCare Macquarie Park MasterplanSSD-46561712-Mod-1
Amendment of Condition A23 Development Staging to create a new sub-stage to incorporate subdivision ahead of the detailed development stage.
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
142 documents in 9 folders, each on the NSW Planning Portal
Notice of Exhibition2
EIS29
- A. Aboriginal and Cultural Heritage Assessment
- Architectural Drawings
- B. Acoustic Impact Assessment
- BaptistCare Certificate of Registration
- C. Arboricultural Impact Statement
- CIV Estimate
- D. Archaeological Report
- E. Architectural Urban Design Report
- Environmental Impact Statement
- F. Civil Concept Design
- G. Community Engagement Report
- H. Crime Prevention Through Environmental Design Report
- I. Ryde DCP 2014 – Compliance Assessment
- J. Ecological Impact Assessment (BDAR)
- K. Environmentally Sustainability Development Report
- L. Flood Impact Assessment
- L. Flood Risk Assessment
- M. Geotechnical Assessment
- N. Landscape Design Report
- O. Preliminary Contamination Site Investigation
- P. Services Concept Design
- Q. Social and Economic Impact Assessment
- R. Site Survey
- S. Traffic and Transport Impact Assessment
- T. Visual Impact Assessment
- U. Wind Impact Assessment
- V. Construction and Demolition Waste Management Plan
- W. Operational Waste Management Plan
- X. Clause 4.6 Variation Request
Response to Submissions20
- Appendix A - Submissions Register
- Appendix B - Detailed Response to Submissions
- Appendix C - Architectural Detailed Response to Submission
- Appendix D - Revised Reference Scheme
- Appendix E - Revised Concept Drawings
- Appendix F - Arboricultural and Landscape Impact Statement
- Appendix G - Revised Design Guidelines
- Appendix H - Acoustic Response to Submissions Statement
- Appendix I - Private Domain View Sharing Report
- Appendix J - Wind Response to Submissions Statement
- Appendix K - Revised Clause 4.6 Variation Request
- Appendix L - Traffic Response to Submissions Statement
- Appendix M - Flooding Response to Submissions Statement
- Appendix N - Civil and Stormwater RTS Statement
- Appendix O - Geotechnical Response to Submissions Statement
- Appendix P - Housing SEPP Compliance Table
- Request RTS Letter
- Request RTS Letter
- Request RTS Letter (03.03.23)
- Submissions Report
Agency Advice22
- 20250613 - TfNSW Response Letter -RTS - SYD24_00141
- BaptistCare Macquarie Park Masterplan (SSD-46561712)
- BaptistCare Macquarie Park Masterplan - CASA REPLY
- BaptistCare Macquarie Park Masterplan SSD-46561712_1
- CPHR advice on Amendment Report
- CoR Cover Letter - Baptistcare SSD
- CoR Submission - Attachment 1 - Baptistcare Macquarie Park
- CoR Submission Cover Letter - Baptistcare Macquarie Park
- CoR- Attachment 1 - Baptistcare SSD
- DET Schools Response
- DPE Water Response - BaptistCare Macquarie Park Masterplan
- EHG response - Baptistcare Macquarie Park
- FRNSW - BaptistCare Maquarie Park - No Further Comment
- Fire and Rescue Submission - BaptistCare Macquarie Park Masterplan
- HNSW ACH - Amendment - BaptistCare SSD-46561712 (HMS 10675)
- Heritage NSW ACH - Baptistcare Macquarie Park
- NSW DCCEEW Water Group response
- NSW SES - Response BaptistCare Macquarie Park
- NSW SES BaptistCare Macquarie Park Masterplan
- SDRP Advice letter - Macquarie Park
- SSD-46561712 - BaptistCare Macquarie Park HMS 10634
- TfNSW Response - Baptistcare Macquarie Park
Amendments50
- Affordable Housing Management Agreement Letter
- Amended Application_20250423020824
- Amendment Report
- Appendix A - Updated Project Description
- Appendix AA - Updated Wind Impact Assessment
- Appendix B - Updated Statutory Compliance Table
- Appendix BB - Public Art Strategy
- Appendix C - Amended Mitigation Measures
- Appendix CC - Updated Construction and Demolition Waste
- Appendix D - Clause 4.6 Variation Request
- Appendix DD - Updated Operational Waste Management Plan
- Appendix E - Updated Architectural Drawings
- Appendix EE - Asbestos Clearance Certificate
- Appendix EE - Asbestos Management Plan
- Appendix EE - Contamination Investigation Summary
- Appendix EE - Detailed Site Investigation
- Appendix EE - Overarching Remedition Action Plan
- Appendix EE - Preliminary (Stage 1) Site Investigation
- Appendix F - Reference Scheme
- Appendix F - Updated Urban Design Report Part 1
- Appendix F - Updated Urban Design Report Part 2
- Appendix FF - Place Strategy
- Appendix G - Updated Arboricultural Impact Assessment
- Appendix GG - Community Needs Strategic Alignment
- Appendix H - Updated Traffic and Transport Assessment
- Appendix HH - Retail Impact Assessment
- Appendix I - Updated Flood Risk and Impact Assessment
- Appendix II - Heritage Impact Assessment
- Appendix J - Design Guidelines
- Appendix JJ - Geotechnical Report
- Appendix K - Response to Submissions Table
- Appendix KK - Surface and Ground Water Impact Assessment
- Appendix L - Updated Landscape Design Report
- Appendix M - Updated ACHAR Part 1
- Appendix M - Updated ACHAR Part 2
- Appendix N - Updated Ecological Impact Assessment (BDAR)
- Appendix O - Acoustic Impact Report
- Appendix P - Updated Archaeological Report
- Appendix Q - Updated Civil Concept Design
- Appendix R - Community Engagement Report
- Appendix S - CPTED Report
- Appendix T - Updated Ryde DCP 2014 - Compliance Assessment
- Appendix U - Updated ESD Report
- Appendix V - Connecting With Country Strategy
- Appendix W - Updated Building Services Masterplan Report
- Appendix X - Access Report
- Appendix Y - Updated Social and Economic Impact Assessment
- Appendix Z - Updated Visual Impact Assessment
- Estimated Development Cost
- SSD46561712 Amendment Acceptance Letter
Additional Information11
- A - Detailed Response to Comments
- B - Revised Staging Drawings
- C - Revised Private Domain View Sharing Report
- D - Revised Shadow Studies and Solar Analysis
- E - Morling College Tower Diagram
- F - Traffic Addendum Response Letter
- Final RFI Response Letter_SSD-46561712
- G - Contamination Addendum Response Letter
- Lot 5 GFA Plan
- Request for Additional Information 29-01-2026
- Revised Design Guidelines
What's near it
Where it is
- Suburb
- Macquarie Park
- Council area
- Ryde
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.