On the map
State significant development

Apollo Place Data Centre

Decided: approved on 9 Oct 2025Data centres

Where it is in the process

Approved on 9 Oct 2025

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination9 Oct 2025 (done)
  9. Approved9 Oct 2025

What it proposes

The department's description

Demolition of existing buildings and construction and operation of a 45-megawatt data centre

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

4 submissions: 2 from the public, 1 from organisations and 1 from public authorities

Object2
Support1
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

107 documents in 9 folders, each on the NSW Planning Portal

Early Consultation2
Notice of Exhibition1
SEARs2
EIS44
Response to Submissions2
Agency Advice15
Additional Information34
Determination6
Management Plans and Strategies1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.