Decided: approved on 27 Feb 2003Transport

Where it is in the process

Approved on 27 Feb 2003

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination27 Feb 2003 (done)
  10. Approved27 Feb 2003

What it proposes

The portal gives no description.

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Administrative ChangeG96/00145/Z-Mod-1

Decided: approved on 28 Jun 2012 by Dir(MIA)

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.