45-57 Moxon Road Multi-Level Warehouse
Where it is in the process
Approved on 19 Jul 2024
What it proposes
The department's description
Construction and operation of a two-storey warehouse and distribution facility at 45-57 Moxon Road in Punchbowl, comprising:
• two buildings
• associated office space and amenities
• supporting infrastructure, services and landscaping.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
10 submissions: 7 from the public, 2 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
Modification 1 Changes to SignageSSD-55266460-Mod-1
Modification to amend building, business identification and wayfinding signs
Its 4 documents
4 documents in 3 folders, each on the NSW Planning Portal
Agency Advice1
Determination2
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
134 documents in 13 folders, each on the NSW Planning Portal
Early Consultation1
Notice of Exhibition1
Request for SEARs1
EIS34
- Appendix A - SEARs Compliance
- Appendix AA - Service Infrastructure Assessment
- Appendix B - Architectural Plans
- Appendix BB - Civil Engineering Report
- Appendix C - Statutory Compliance Table
- Appendix CC - Social Impact Assessment
- Appendix D - Mitigation Measures
- Appendix DD - Stakeholder Engagement Report
- Appendix E Engagement Summary Table
- Appendix EE - Resilience and Hazards Report
- Appendix F - Design Report
- Appendix FF - Light Spill Assessment
- Appendix G - Survey Plan
- Appendix H - ESD Report
- Appendix I - Regulatory Compliance Report
- Appendix J - Accessibility Review Report
- Appendix K - Arboricultural Impact Assessment
- Appendix L - Visual Impact Assessment
- Appendix M - Traffic and Transport Report
- Appendix N - Landscape Plans
- Appendix O - BDAR
- Appendix P - Air Quality Impact Assessment
- Appendix Q - Noise and Vibration Impact Assessment
- Appendix R - Geotechnical Investigation
- Appendix S - Acid Sulfate Soil Management Plan
- Appendix T - Detailed Site Investigation
- Appendix U - Remediation Action Plan
- Appendix V - Preliminary LTEMP
- Appendix W - Waste Management Plan
- Appendix X - Hazardous Building Materials Survey
- Appendix Y - ACHAR
- Appendix Z - Statement of Heritage Impact
- Cost Summary Report - Final
- Environmental Impact Statement - Final
Response to Submissions11
Agency Advice17
- Advice on EIS (Council)
- Advice on EIS (DPE Water)
- Advice on EIS (DPI Fisheries)
- Advice on EIS (EHG)
- Advice on EIS (FRNSW)
- Advice on EIS (Sydney Water)
- Advice on EIS (TfNSW)
- Advice on EIS (Water NSW)
- Advice on RTS (Canterbury-Bankstown Council)
- Advice on RTS (DPE Water)
- Advice on RTS (DPI Fisheries)
- Advice on RTS (EHG)
- Advice on RTS (FRNSW)
- Advice on RTS (TfNSW)
- BCS Advice - RFI 45-47 Moxon Road, Punchbowl SSD-55266460
- Councils Traffic Comments (160424)
- TfNSW Additional Advice (230424)
Additional Information18
- 090424 Response on vehicle restriction
- 120424 Acoustic Response to RFI
- 120424 Noise Report
- Appendix A Architectural Plans
- Appendix B BDAR
- Appendix C Civil Engineering Report
- Appendix D Civil Engineering Plans
- Appendix E Flood Analysis Plans
- Appendix F Community information session outcomes
- Appendix G FMP & FERP
- Appendix H NVIA
- Appendix I Interim Audit Advice
- Appendix J Transport Technical Note
- Final Noise Report
- Operational Traffic Generation Profile
- Request for Additional Information 041223
- Response to Traffic Impact RFI
- Supplementary RFI Response - 45-57 Moxon Road, Punchbowl
Determination6
Management Plans and Strategies32
- App B updated (including new CO13924.02-C652-A)
- App C and D
- Approval of CEMP
- Approval of Design Flood Verification Report
- Approval of Detailed Design Road Safety Audit
- Approval of Plan (SSD-55266460-PA-16)
- Approval of Plan Strategy or Study (1)
- Approval of Plan Strategy or Study_22092026_022819
- Approval of the On-Site Traffic Control Plan
- B56 DFVR rev C 20241017
- B6 OSTCP rev04 20250129
- B9(a) Road Safety Audit Rev 3
- C2 CEMP (excl. Appendices) ESCP v4 CLEAN
- C2 CEMP App H ESCP v4
- C2 CEMP App I pt 2
- C2 CEMP App I pt 3
- C2 CEMP App I pt 4
- C2 CEMP App I pt 5
- C2 CEMP App I pt 6
- C4 Revised CEMP & E&SCP App Letter 060325
- CEMP
- CEMP App A - F
- CEMP App G
- CEMP App H
- CEMP App I pt 1
- CEMP App J - K
- EROSION SEDIMENT CONTROL v6 - STAGE 2_Clean
- OTMP Post Approval Letter
- OTMP_Appointment of Experts
- Operational FERMP
- P26136 - Punchbowl 45 Moxon Road OCHP - FINAL
- Technical Note on Project Team Decisions to RSA
Independent Reviews and Audits2
Notifications6
What's near it
Where it is
- Suburb
- Punchbowl
- Council area
- Canterbury-Bankstown
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.